File #: BDGT 21-01    Version: 1 Name: PD Administration Building & Emergency Communication Center
Type: Budgetary Transfer Status: Passed
File created: 11/24/2021 In control: City Council Regular Meeting
On agenda: 12/7/2021 Final action: 12/7/2021
Title: The Mayor and City Council shall discuss and take action to approve a budget not to exceed $25,388,785 for the new Police Administration Building and Emergency Communication Center and to revise project #38049 to solely include the construction, IT/Communications, and complete outfitting (PSAP consoles and FF&E) of the new Police Administration Building and Emergency Communication Center. Discussion and Action.
Sponsors: Jennifer Brown, James Hughes
Indexes: Community Resources and Quality of Life Amenities, Economic Development, Fiscal Policies and Management, Safe and Livable Community , Well Planned Quality Growth and Development
TITLE
The Mayor and City Council shall discuss and take action to approve a budget not to exceed $25,388,785 for the new Police Administration Building and Emergency Communication Center and to revise project #38049 to solely include the construction, IT/Communications, and complete outfitting (PSAP consoles and FF&E) of the new Police Administration Building and Emergency Communication Center. Discussion and Action.

AGENDA ITEM DESCRIPTION
With this new facility we are seeking to meet our growth needs until we reach a population of approximately 150,000 - 200,000. Future growth, south of Ak-Chin will likely require a Police Annex to service this area in the years/decades to come.
The general market is seeing a significant rise in construction costs due to material supply chain issues and labor shortages. To date, the all in cost has risen to nearly $25.4 million. The graph below provides our original funding and suggested funding to cover cost escalation.
Additional
Current budget
allotted Projected Projected Budgeted needed &
space need cost source
Police Station 16,300 sf* 24,305 sf $10,906,260
Dispatch 1,700 sf 7,228 sf $ 4,543,947
Soft Cost $ 1,900,000
Site Improvements $ 3,538,578
Technology $ 1,500,000
FF&E $ 1,500,000
Contingency $ 1,500,000
Total $25,388,785 $20,000,000 $ 5,388,785
General Fund $10,000,000 $ 568,985 (FY 23)
Land Sale Proceeds** $ 6,431,714 $ 500,000
Police Impact Fees*** $ 3,568,286 $ 2,161,800
FY20/21 ****Cont...