File #: CON 16-51    Version: 1 Name: Facilities improvements JOC
Type: Contract Status: Passed
File created: 10/24/2016 In control: City Council Regular Meeting
On agenda: 11/21/2016 Final action: 11/21/2016
Title: The Mayor and City Council shall discuss and possibly take action on approving a cooperative agreement and Addendum with FCI Constructors, Inc. for various job order contract services for the fire stations pursuant to Section 3-223, “Cooperative Purchasing” of the City Code in an amount not to exceed $350,000. The expenditure will be paid from the Capital Projects Fund-Fire Support Services, budget line (35022528-67741-32029),(35022528-67730), (35022528-67741-32028) and budget line (35022528-67720--32030). Construction that falls under General budget will be paid from budget line (10022528-54430). Discussion and Action.
Sponsors: Brady Leffler
Indexes: Safe and Livable Community
Attachments: 1. Contract, 2. Purchasing Summary, 3. FCI Constructors - 2015-16000 JOC Agreement - Executed
TITLE
The Mayor and City Council shall discuss and possibly take action on approving a cooperative agreement and Addendum with FCI Constructors, Inc. for various job order contract services for the fire stations pursuant to Section 3-223, “Cooperative Purchasing” of the City Code in an amount not to exceed $350,000. The expenditure will be paid from the Capital Projects Fund-Fire Support Services, budget line (35022528-67741-32029),(35022528-67730), (35022528-67741-32028) and budget line (35022528-67720--32030). Construction that falls under General budget will be paid from budget line (10022528-54430). Discussion and Action.


AGENDA ITEM DESCRIPTION
This request is grouping several construction projects under a Job Order Contract (JOC) to save on management fees so it is tied to a single project instead of management fees for several projects.
These projects are:
· Generator Replacement at Station 572. This generator has reached its service life and is due for replacement. The expenditure will be paid from the Capital Projects Fund-Fire Support Services, budget line (35022528-67741-32029)
· Station 571 floor and blacktop improvements. The floor at this station is in need of resurfacing/replacing and all exterior asphalt needs resurfaced and striped. Floor is to be replaced with an epoxy base that is durable and cleanable. The expenditure will be paid from the Capital Projects Fund-Fire Support Services, budget line (35022528-67720-32030).
· Station 574 floor, concrete and blacktop improvements. The floor at this station is in need of resurfacing/replacing, all exterior asphalt needs resurfaced and striped and entry to the bay needs concrete addition to replace damaged asphalt. Floor is to be replaced with an epoxy base that is durable/cleanable and 8” concrete with microfiber will replace the damaged asphalt area. The expenditure will be paid from the Capital Projects Fund-Fire Support Services, budget line (35022528-67730).
· Remodeling of SCBA(Self...